This is a Garage Renovation project we started yesterday 7/12/17.  The approximate size of the garage is 10×20 and client wants us to remove all existing sheet rock, hang new sheet rock on all walls and ceiling (including tape, float, and sand), cut out 2 window holes in brick siding, install two windows, and install 4 electrical outlets.  We promised client project would be done by 7/26 which is 2 weeks, but we’re hoping to be done in 7 days.  Here are a few pictures of Day 1 – Demolition.

Today, we’ll cut out the windows, and lay the electrical work for the outlets.